Takht Jamshid Petrochemical Complex has been constructed in two phases. The first phase included the production of 30,000 tons of SBR and 12,000 tons of PBR, which was commissioned between 2012 and 2014. The second phase, with a capacity of 50,000 tons of PBR, was fully designed and executed using domestic expertise, launched in 2017, and commissioned in 2019.

_

Description of Execution Works

Icon8

Contract Period: 2014–2015

  • Execution of lean concrete works and concrete equipment foundations for the substation and control room building complex
  • Execution of excavation, backfilling and compaction, and construction of equipment and structure foundations
  • Execution of all building works (structures, mechanical installations, fire extinguishing system), commissioning, and handover of the building