introduce

Project Description

_

Exir sanat Company, in collaboration with the Ukrainian company KotelEnergiProm, executed the modernization project of two boilers at Isfahan Steel Company’s power plant. Carried out under an EPC approach, this project increased production capacity from 70 to 100 tons of steam per hour. Despite challenges such as sanctions and price fluctuations, the company successfully completed and delivered the first phase of the project through precise planning. This project has played a key role in optimizing the performance of Isfahan Steel’s central power plant.

_

Industrial Operations Description 

Icon8

Contract Duration: 2010–2011

  • Execution of reconstruction, major maintenance, capacity increase, and modernization of Boilers No. 3 and 4 at the central power plant of Isfahan Steel Company, carried out during 2010–2011.