Project Description

_

Alay Mahestan Petrochemical Company, located in the South Pars region (20 km from Kangan), is under construction with an annual capacity of 450,000 tons of propylene and PP-propylene. This unit represents the first PDH facility in the country for propane production and will play a key role in supplying feedstock and developing the regional petrochemical value chain.

_

Industrial Operations Description 

Icon8

Contract period: 2023–Present

  • Underground piping70,000 inches in diameter (including sandblasting, coating, fit-up, welding, and testing)
  • Civil works100,000 cubic meters of earthworks
  • EquipmentConstruction and installation of manholes and valve pits
_

Description of Civil Works

Icon8

Contract period: 2021–present

  • Civil worksCivil works: 22,000 m³ concrete, 160,000 m³ excavation, 4,000 tons of reinforcement, 8,000 m² flooring.
  • StructuresPiping, equipment/floating tank foundations, bagging structure, powder silo, TEAL building.
  • BuildingsFire station, warehouse, central workshop, administrative building, mosque, restaurant (11,000 m² of built-up area)
  • installationsArchitecture, mechanical, and electrical works