Fajr Petrochemical Company was established in 1998 with the aim of supplying electricity and steam to the petrochemical plants in the Special Economic Zone of Bandar Imam Khomeini. Its first phase was commissioned in 2002, and with the expansion of petrochemical plants, the company’s services were extended to Sites 2 and 3 of the zone as well.

_

Description of Execution Works - Fajr 1

Icon8

Contract Period: 2006–2008

Building, Installation, and Execution Contracts

  • Construction and Installation of Chimney
  • Installation of Steel Structure
  • Installation and Commissioning of Load Shedding System
  • Construction of 125 MW Gas Unit and BOP (Balance of Plant)
  • Supply of Materials and Equipment
  • Pipeline Installation
_

Description of Execution Works - Fajr 2

Icon8

Contract Duration: 2009–2008

Installation of recovery and auxiliary boilers

  • Complete installation of two Doosan Korea waste heat recovery boilers (manufactured by MAPNA Boiler), each with a capacity of 440 tons per hour.
  • Installation of one auxiliary boiler with a capacity of 160 tons per hour.
  • Installation of all common and auxiliary equipment along with accessories, weighing over 3,500 tons.
  • Pre-commissioning and assistance in commissioning.
_

Description of Execution Works - Fajr 1,2

Icon8

Contract period: 2010–2011

Construction of the mosque and restaurant building

  • Execution of all building operations including civil works, electrical installations, mechanical installations, fire-fighting system, commissioning, and handover of the building.