introduce

Project Description

_

Arvand Petrochemical Company was established with the objective of supplying raw materials for chemical and downstream industries to both domestic and export markets. It is located on a 108-hectare site in Zone 3 of the Bandar Imam Special Economic Zone. The complex consists of Chlor-Alkali, Ethylene Dichloride (EDC), Vinyl Chloride Monomer (VCM), PVC Suspension, and PVC Emulsion units, along with utility and offsite facilities, and is recognized as one of the largest PVC chain producers in the Middle East.

_

Description of Execution Works

 
 
Icon8

Contract Period: 2009

  • Execution of earthworks, concreting, and fencing
_

Description of Execution Works

Icon8

Contract Period: 2009–2010

  • Execution of Arvand Petrochemical export pipeline works, including civil works, steel structures, mechanical installations, electrical, and instrumentation
_

Pipe Rack Building Construction Project

Icon8

Contract Period: 2008

  • Execution of all building works including structures, electrical installations, mechanical installations, fire extinguishing system, commissioning, and handover of the building