introduce

Project Description

_

South Pars Phase 13 Refinery, located in the Tombak region, 220 km from Bushehr, has a processing capacity of 2 billion standard cubic feet per day (SCFD). The complex includes all processing units, auxiliary facilities, and infrastructure required for the production of export gas, ethane (as petrochemical feedstock), propane, butane, and gas condensates.

The project execution commenced in 2010 by a consortium comprising Petro Paydar Iranian, MAPNA, and SADRA, under the management of Pars Oil and Gas Company (POGC), and was implemented as an EPCC contract, covering all stages from engineering design to commissioning.

_

Industrial Operations Description 

Icon8

Contract Period: 2012–2021

Project execution carried out in Units 106, 108, 121, 123, 124, 126, 127, 128, 129, 130, 131, 132, 145, 146, and 160

  • Fit-up and welding of more than 260,000 inch-diameter of carbon steel and stainless steel piping, including painting, insulation, and testing
  • Fabrication and installation of carbon steel and stainless steel supports
  • Installation of static and rotary equipment along with internal and external mechanical accessories (exceeding 1,500 tons)
  • Completion of installation, pre-commissioning, and commissioning support of equipment (amounting to 8,000 tons)
  • Execution of fabrication, installation, punch list clearance, and pre-commissioning of mechanical equipment, piping, electrical, instrumentation, and control systems
  • Commissioning of Trains 3 and 4 of Unit 108 (Sulfur Recovery Unit)
_

Construction and Installation Contracts

Icon8

Contract Period: 2018–2022

  • Execution of aboveground pipelinesExecution and completion of pre-commissioning and commissioning support of aboveground pipelines
  • Execution of LPG and fuel gas pipelinesExecution of piping works for LPG and fuel gas lines of Unit 172, Section B, including piping, valve installation, heat treatment, testing, and insulation
  • 36-inch underground pipelineExecution of civil works and piping for the 36-inch underground condensate pipeline, including earthworks, piping, valve installation, heat treatment, testing, and insulation
_

MAPNA Group Contracts

Icon8

Contract Period: 2019–2021

Contracts for the development of certain units of South Pars Phase 13 were concluded between Niropars (representing MAPNA Group) and Exir Sanat Bakhtari Company, with the scope of work including the construction of utility and process units.

  • Installation of mechanical equipment and piping
  • Installation of cooling water equipment
  • Execution of underground piping
  • Provision and maintenance of manpower
  • Hydrotesting, refractory works, and equipment insulation
_

Description of Civil Works

Icon8

Contract Period: 2014–2021

  • Execution of 120,000 cubic meters of earthworks, including excavation and backfilling
  • Supply and execution of 18,000 cubic meters of concrete for concrete structures and paving
  • Construction of 28,000 meters of asphalt road in Units 129, 130, 131, 145, 146, 111, 108, and 106 of Phase 13
  • Execution of equipment and structure foundations, fabrication of precast components, and steel structures
  • Application of Glass Flake protective coatings and alumina concrete for sulfur pit structures
  • Execution of sealing and leak testing of structures
  • Execution of concrete paving, landscaping, substructure works, and gravel spreading
  • Execution of slope protection (stone pitch) and internal unit roads
  • Painting of concrete surfaces and execution of final finishing works of the UFP Room building
  • Execution of steel structure for Unit 106, Main Shelter, Piperack, and Main Pipe Support
  • Completion of steel structure works for the remaining units
_

Civil Contracts of Petro Paydar Iranian

Icon8

Contract Period: 2017–2020

  • LandscapingExecution of supplementary civil works and site preparation activities for Tombak service and export port
  • Building and equipment foundationExecution of general civil works and foundations for Unit 149, Unit B4, and the flare at Tombak site
  • Completion of building worksExecution of supplementary civil works and site preparation for the Tombak service and export port
_

Civil Contracts of Mapna

Icon8

Contract Period: 2017–2020

  • Civil and building works
  • Execution of concrete trench and two silos of Unit 144
  • Execution of civil works in Units 129, 132, 108, 106, and 111